Dates are not being automatically refreshed RRS feed

  • Question

  • Dates are not being automatically refreshed on to the tasks when we change the dates within the PLAN1 project plan. Additionally, when linking to other project plans, for example PLAN2, the dates are not automatically refreshing as well.

    Thursday, April 18, 2013 10:37 AM

All replies

  • John,

    Just a thought. Do these tasks have a constraint?  Put the field "Constraint Type" on the view and see if the constraint may be holding the task dates frozen? Also, are you sure you actually have recalculated the schedule?


    --rms www.rmschneider.com

    Thursday, April 18, 2013 3:34 PM
  • John,

    In addition to Rob's questions, do the tasks have an actual start date (i.e. indicating they have started)? If so, then any predecessors are null and void.

    Also, what happens when both Plan1 and Plan2 are open? Do the dates update?

    By the way, why did you repost? You asked this question yesterday and were asked the same or similar questions by Julie and never responded.

    John