All Projects Category and RBS RRS feed

  • Question

  • Hi, we are just about to retrospectively setup our RBS.  Can i confirm that giving someone the All Projects category effectively "trumps" the permission limitations the have via a RBS value?  I want to be able to assign RBS values to our team and then remove the All projects category for them.  I assume that is a practical order to do this?

    Steve

    Wednesday, October 7, 2015 8:32 AM

All replies

  • Hi Steve,

    Once assigned to users, the RBS has an effect only if the categories associated to the users' groups are configured based on the RBS. So if you assign RBS value to users belonging to a category with no project restriction based on the RBS, it will have no effect at all.

    I suggest to configure the category, then assign RBS values to a few test users, assign also the category to the users' group and see if it behaves as expected.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    Wednesday, October 7, 2015 8:47 AM
    Moderator