%Complete is not updating , if remaining work changes to "0hrs" if it is a Fixed Duration.
Venkat. you probably notice that the Gantt chart shows a dotted line after the completed 1 day of work - filling the remaining days of your fixed duration task. No ...Answered | 2 Replies | 2612 Views | Created by Venkatrao P - Monday, March 4, 2013 1:45 PM | Last reply by Venkatrao P - Tuesday, March 5, 2013 7:23 AM -
0 Votes
fixed duration and unit
Hi all, is there any way to arrange task type as "fixed duration and unit" .. there is only fixed duration,unit or work, ...Unanswered | 1 Replies | 620 Views | Created by likli - Wednesday, April 12, 2017 10:38 AM | Last reply by Guillaume Rouyre [MBA, MVP, MCC] - Wednesday, April 12, 2017 1:18 PM -
0 Votes
Project Server 2010: Resources Assigned Incorrectly to Fixed Duration Tasks
10 days. What causes this? Am I not understanding how fixed duration tasks work? I would think the assigned resource would ...Answered | 4 Replies | 6616 Views | Created by Bryan J. Campbell - Sunday, July 31, 2011 11:54 PM | Last reply by epmXperts - Monday, November 19, 2012 11:20 PM -
0 Votes
PWA schedule summary tasks - change to show duration in hours
Hi Guillaume, Thanks for this info. I didn't specify, but it's actually the duration column summary tasks that are showing in days - even although the ...Answered | 2 Replies | 1571 Views | Created by Mark Woodhouse - Wednesday, February 18, 2015 10:29 AM | Last reply by Mark Woodhouse - Wednesday, March 18, 2015 4:03 PM -
0 Votes
fixed duration + resources question
using fixed units (default) i have tried fixed duration as well as fixed work, along with both effort driven and not, so far it has not ...Answered | 2 Replies | 688 Views | Created by efrizzell - Monday, December 1, 2014 3:31 PM | Last reply by efrizzell - Monday, December 1, 2014 4:21 PM -
0 Votes
Fixed work duration doesn't change when adding resources...
Hello, I m bit confused first you said all sub tasks are Fixed Work, then you say they are Fixed Duration and Non Effort Driven, does ...Answered | 15 Replies | 22104 Views | Created by Fuller Electric - Monday, February 28, 2011 6:21 PM | Last reply by Dale Howard [MVP] - Thursday, June 2, 2011 9:38 PM -
1 Votes
Scheduling after hours tasks in MS Project & keep duration time
Hi Jan Not that easy. When doing it this way you can use a single resource and schedule out-of-hours work but it wont recognise ...Answered | 3 Replies | 5832 Views | Created by A.W Johnston - Wednesday, November 21, 2012 9:32 PM | Last reply by Jan De Messemaeker - Project MVP - Thursday, November 22, 2012 12:39 PM -
3 Votes
Using fixed-duration tasks to “hard code” resource percentages
hour duration task, it does not mean he's assigned 10%. If it's 4 hours worth of full-time work and he expected to do it in 4 hours, he's ...Answered | 10 Replies | 10103 Views | Created by TresL - Wednesday, July 14, 2010 5:26 PM | Last reply by Steve House - Sunday, July 18, 2010 9:06 PM -
0 Votes
Baseline Duration custom field not calculating duration properly
In cases where Baseline Duration was saved for individual tasks without rolling up to summaries rows - you may have deviations. Applying "Use ...Unanswered | 2 Replies | 3137 Views | Created by Pradeep Gangwar - Wednesday, September 3, 2014 7:18 AM | Last reply by Pradeep Gangwar - Monday, September 8, 2014 5:30 AM -
0 Votes
Can not change work and duration
Options, Schedule. The other choice is to create resources (Resource sheet) and assign the resources to the tasks. Then enter the work estimateUnanswered | 2 Replies | 642 Views | Created by AlexUNIHelp - Friday, April 24, 2015 1:57 AM | Last reply by Julie Sheets - Friday, April 24, 2015 1:44 PM -
1 Votes
Setting specific 'work' on a Fixed Duration Task
I am currently trying to set work (in hrs) for a number of fixed duration tasks in my project plan. Hoping there is a simple answer to this ...Answered | 1 Replies | 4701 Views | Created by DavidWilsonLHDUK - Wednesday, February 22, 2012 2:15 PM | Last reply by Mike Glen - Wednesday, February 22, 2012 3:28 PM -
1 Votes
Display duration in hours
Hello MS Project 2007 experts, Is that possible to display duration in hours / mintues (instead of .5 days)? Could you please guide ...Answered | 5 Replies | 12905 Views | Created by SPJoseph - Thursday, October 6, 2011 8:08 PM | Last reply by Ismet Kocaman - Thursday, October 6, 2011 10:09 PM -
1 Votes
Duration not accurate for summary tasks.
Thanks for the reply and links. The schedule in my question shows the duration greater than the work hours, even though I have multiple resources assigned to certain ...Proposed | 14 Replies | 32098 Views | Created by Peter Pynchon - Monday, June 4, 2012 12:09 AM | Last reply by Roopkumar Kamat - Thursday, August 23, 2012 7:37 PM -
0 Votes
Task percent complete is not getting 100% for fixed duration tasks
duration. Fixed work may give you more "intuitive" behavior. The reason we're using fixed duration is b/c we are ...Answered | 11 Replies | 16631 Views | Created by Sachin Vashishth - Thursday, March 31, 2011 7:45 AM | Last reply by Sachin Vashishth - Tuesday, April 19, 2011 5:57 PM -
0 Votes
WHY you can't edit fixed work tasks in PWA 2010?
I know you cannot edit fixed work tasks in PWA 2010, but I was wondering what the reasoning was behind this. All of my clients use fixed work ...Answered | 2 Replies | 9433 Views | Created by Chad Olson - Thursday, December 23, 2010 6:54 PM | Last reply by HoustonKoppite - Tuesday, February 15, 2011 8:19 PM -
0 Votes
Change in Calendar Calendar Hours Per Day not automatically updating Work Hours
maintained its value of 134.02. What do I need to do for this to change automatically? All tasks should have their Work change automatically. I have all ...Answered | 3 Replies | 874 Views | Created by Dee Nolovich - Thursday, January 21, 2016 4:34 PM | Last reply by Dee Nolovich - Friday, January 22, 2016 4:39 PM -
2 Votes
Fixed units / Fixed work - best practice?
DIFFERENCE BETWEEN 1 AND 5 IS WHEN YOU CHANGE THE DURATION fixed work (1) will keep the amount of work constant and change how many ...Answered | 4 Replies | 4672 Views | Created by AT_lamnea - Monday, August 25, 2014 8:52 AM | Last reply by AT_lamnea - Thursday, August 28, 2014 8:47 PM -
1 Votes
Variable duration tasks
critical path) even if they might seem to be a solution to this one. I am not sure what happens during the "downtime" but suppose nothing happens except that ...Unanswered | 4 Replies | 647 Views | Created by bfhaynes - Wednesday, October 29, 2014 6:25 PM | Last reply by Trevor Rabey - Thursday, October 30, 2014 1:25 AM -
0 Votes
Fixed Work Problems
averaging the amount of work over the duration and entering that into their tasks and timesheets. It only does this if the task is set to Fixed ...Answered | 4 Replies | 9470 Views | Created by LAnneB - Wednesday, January 12, 2011 5:44 AM | Last reply by LAnneB - Wednesday, January 12, 2011 10:32 PM -
1 Votes
Calculating number of resources need from fixed work and fixed duration
I'm still trying to wrap my head around resources. Example: I have a task that I know will take 400 man hours to complete. So, I set Project to ...Answered | 6 Replies | 1200 Views | Created by Sean Gibat - Thursday, July 17, 2014 1:34 PM | Last reply by Guillaume Rouyre [MBA, MVP, MCC] - Thursday, July 17, 2014 3:48 PM