No announcements
Found 919400 threads
-
2 Votes
Purpose of Baseline Estimate Start and Baseline Estimate Finish
your project, Microsoft Project 2010 saves the current values for every task in the Baseline Duration, Baseline Start, Baseline Finish, ...Answered | 4 Replies | 17747 Views | Created by Michael Wharton - Tuesday, March 9, 2010 4:44 PM | Last reply by Dale Howard [MVP] - Thursday, March 11, 2010 2:31 PM -
0 Votes
MS Project 365 Baseline start vs Start
slippage has occurred in your project, Microsoft Project includes a Variance table that will show you this information. If you have saved a ...Answered | 5 Replies | 1181 Views | Created by OxfordAlain - Tuesday, February 5, 2019 6:24 PM | Last reply by Ben Howard [MVP] - Tuesday, February 12, 2019 8:54 AM -
2 Votes
PREVENT BASELINE OVERWRITING - MS PROJECTS 2010 INTEGRATED WITH EPM 2010
hi dale,thanx for response,i do not have a problem in project manager rebaselining project,my only issue is that they should not be able to overwrite there already existing ...Answered | 3 Replies | 5423 Views | Created by anuj astro - Wednesday, May 2, 2012 11:17 AM | Last reply by Dale Howard [MVP] - Wednesday, May 2, 2012 2:56 PM -
1 Votes
Baseline?
/books etc... http://www.microsoft.com/project/en/us/train-learn.aspx And Baseline are not required, it all depends what isAnswered | 2 Replies | 10597 Views | Created by subnodate - Friday, June 4, 2010 5:12 AM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Friday, June 4, 2010 12:48 PM -
0 Votes
Baseline disappears
blog | bookUnanswered | 2 Replies | 714 Views | Created by Projectnewbie - Friday, February 24, 2017 7:55 PM | Last reply by Ben Howard [MVP] - Tuesday, February 28, 2017 6:36 AM -
1 Votes
Baselinestart or baselinestiamated start , which gives the exact baseline date
recommend you use the Baseline Estimated Start field instead. The reason for these recommendations lies in how Microsoft Project 2010 baselines ...Answered | 2 Replies | 6670 Views | Created by Kvingupta - Sunday, October 9, 2011 10:35 AM | Last reply by Ashu_ - Monday, October 10, 2011 7:47 PM -
0 Votes
Baseline dates save in MSP 2003 don't appear in MSP 2010
DavePM -- I'm not sure I fully understand your question. Are you saying that the Baseline Start and Baseline Finish dates have disappeared in your ...Answered | 1 Replies | 9030 Views | Created by DavePM - Friday, June 3, 2011 6:35 PM | Last reply by Dale Howard [MVP] - Saturday, June 4, 2011 12:47 AM -
0 Votes
Master Plan - problem with calendar into Subproject
If the save in the sub-project baseline -
3 Votes
Partial Baseline Rollup Does Not Apply to Resources Baseline Work and Cost?
://forums.techarena.in/microsoft-project/1405831.htm#post5390423 re: "Baseline fields are static". When you do a ...Answered | 7 Replies | 12467 Views | Created by Guy Le Blanc - Saturday, August 20, 2011 8:56 PM | Last reply by Julie Sheets - Thursday, August 25, 2011 12:32 PM -
1 Votes
User can not save baseline, but can change baseline fields and delete task with baseline values
fields manual changes That is a BIG issue, we has not expecting this kink of problem using Project Professional and Project Online. But, as several ...Answered | 2 Replies | 732 Views | Created by Ricardo Anastácio - Tuesday, November 29, 2016 9:48 PM | Last reply by Ricardo Anastácio - Wednesday, November 30, 2016 2:31 PM -
2 Votes
2010 save as 2007 Baseline fields
on Baseline Start/ Baseline Finish for the new task. Is my repro similar to what you did? It will be helpful to have your repro steps to confirm that this issue ...Answered | 5 Replies | 11827 Views | Created by Winson, PMP,PMI-SP,MCTS - Wednesday, January 20, 2010 2:38 AM | Last reply by Johnny Rajkumar - Monday, January 25, 2010 5:40 PM -
0 Votes
Earned Value Managment - Scope Change and Project Re-Baseline
working on detailed schedule update processes around Earned Value Management and have come across what seems to be an anomaly in Microsoft Project. When ...Unanswered | 2 Replies | 6650 Views | Created by Mike Agnello - Wednesday, July 11, 2012 2:01 PM | Last reply by Mike Agnello - Monday, July 16, 2012 1:31 PM -
1 Votes
Missing baseline labels
There is a problem with Microsoft Project 2010 destroying baseline references that have been previously set in a schedule. For some unexplainedAnswered | 7 Replies | 7664 Views | Created by Dan the Analyst - Thursday, June 28, 2012 11:19 PM | Last reply by Dan the Analyst - Tuesday, July 10, 2012 5:31 AM -
1 Votes
Copy Baseline(x) to Baseline0
Baseline set of fields. After clicking the OK button, and then returning to the dialog, I see the last saved on date to the right of the Baseline item. Is your ...Proposed | 9 Replies | 1222 Views | Created by acampostrini - Wednesday, September 5, 2018 1:12 PM | Last reply by Dale Howard [MVP] - Wednesday, February 26, 2020 6:24 PM -
0 Votes
Project Server 2013 Project baseline
Hello, You can restrict the protected baselines based on user access:Answered | 1 Replies | 910 Views | Created by arun_2014 - Wednesday, December 9, 2015 2:38 PM | Last reply by PWMather - Wednesday, December 9, 2015 3:03 PM -
1 Votes
MIM Config Documenter tool now availiable on GitHub
made since a specific baseline!! • Build confidence in getting things right when making changes to the deployed solution!! You can find the ...Discussion | 0 Replies | 2730 Views | Created by Nilesh Ghodekar (MSFT) - Tuesday, June 6, 2017 6:29 PM -
0 Votes
Possible to Name a Baseline
Hello, Renaming the default "Baseline" to "Baseline 10" baseline names is not possible. You can give the default baseline ...Answered | 3 Replies | 1312 Views | Created by SmokeyJoe101 - Monday, June 22, 2020 1:45 PM | Last reply by SmokeyJoe101 - Tuesday, June 23, 2020 8:42 PM -
1 Votes
Baseline setting
Hi Dale, Has there been any improvements to this over time. We are using Project Online. Requirement is to trigger an approval for a baseline ...Answered | 4 Replies | 6071 Views | Created by sheelaj - Monday, March 19, 2012 6:08 AM | Last reply by Abhijeet Mohite - Wednesday, July 26, 2017 9:20 AM -
0 Votes
Project Server 2013 Baseline
store in project custom fields the baseline save dates. YouUnanswered | 1 Replies | 895 Views | Created by arun_2014 - Thursday, January 14, 2016 7:00 AM | Last reply by Guillaume Rouyre [MBA, MVP, MCC] - Thursday, January 14, 2016 8:50 AM -
0 Votes
PS 2010 - Task Resource - Maintain History
Mohsin -- The only way to handle this is to save an extra copy of your project as an MPP file immediately after you baseline the project. The MPP ...Answered | 1 Replies | 5973 Views | Created by Mohsin Raza J82 - Wednesday, June 29, 2011 8:21 AM | Last reply by Dale Howard [MVP] - Wednesday, June 29, 2011 12:27 PM