Add a New Server to a Farm with all Patches till March 2016 CU
/powershell-script-to-display-version-info-for-installed-sharepoint-product-and-language-packs/ I believe your problem is related to the Language pack. Check with ...Answered | 2 Replies | 800 Views | Created by Rkakkar - Tuesday, May 2, 2017 7:06 AM | Last reply by Rkakkar - Saturday, July 29, 2017 1:01 PM -
0 Votes
Custom Flag field - if Baseline Work exceeds a certain duration
Karen, Sure, no problem. You need to know that Project stores all time based data in minutes, so even though the display may show duration values in hours or days, ...Answered | 3 Replies | 662 Views | Created by Karen Rolling - Tuesday, October 27, 2015 4:40 PM | Last reply by John - Project - Tuesday, October 27, 2015 8:39 PM -
0 Votes
Baseline display problem
Problem... I was able to access and write to the timephased baseline fields in each of my subprojects, but given that I entered this baseline data (via VBA) and I did not ...Unanswered | 4 Replies | 2849 Views | Created by Spiro Theopoulos - Wednesday, May 29, 2013 6:08 PM | Last reply by Spiro Theopoulos - Thursday, June 6, 2013 11:45 PM -
0 Votes
Removing tasks after a baseline is set
no longer required for the project. You can use these either to filter out those tasks so they do not display in the current plan view - or to select them for partial baselining if ...Answered | 3 Replies | 6512 Views | Created by Shawn.Gilbert - Thursday, November 15, 2012 4:45 PM | Last reply by Shawn.Gilbert - Friday, November 16, 2012 12:42 PM -
3 Votes
Tracking Gantt don't display the newest baseline
How do I display in my Tracking Gantt the newest baseline (B) and not the older (A)?Answered | 5 Replies | 13809 Views | Created by Abilio de Assis - Sunday, August 22, 2010 1:46 PM | Last reply by Abilio de Assis - Sunday, August 22, 2010 11:31 PM -
0 Votes
how to check which installations installed in a sharepoint farm using powershell
for the patch baseline from the registry and allows to identify component # PowerShell script to display SharePoint products from the ...Answered | 3 Replies | 2269 Views | Created by adilahmed - Sunday, March 6, 2016 6:06 PM | Last reply by Waqas Sarwar(MVP) - Monday, March 7, 2016 3:31 PM -
0 Votes
Baseline Configuration Analyzer setup problem
I am following the MS SBS 2008 to SBS 2011 migration guide and everything is going well until I try to run the MS Baseline Configuration Analyzer 2.0. It installed and opens OK, ...Answered | 1 Replies | 3554 Views | Created by 2G - Friday, July 15, 2011 1:42 PM | Last reply by Santhosh Sivarajan- - Friday, July 15, 2011 3:02 PM -
0 Votes
Problem in baseline - MSProj 2010
baseline, genereated the baseline and then I pusblished the project. I don't have a specific step by step, it's a intermittent ...Answered | 10 Replies | 8587 Views | Created by rtorres_practicar - Friday, June 10, 2011 1:16 PM | Last reply by rtorres_practicar - Tuesday, June 14, 2011 4:35 PM -
2 Votes
Baseline: unresolved configuration item reference
Hello You have to import both CI and Baseline in DCM they have to be packed in one single CAB file. The CI and the ...Answered | 10 Replies | 8101 Views | Created by linlin_dl - Thursday, April 28, 2011 9:31 AM | Last reply by SCCM-2007 - Tuesday, May 31, 2011 7:44 AM -
0 Votes
Deploy Configuration baseline to Collection problem
When I try to deploy Configuration baseline to Collection problem none of my collections appears to be selected . I can't figure out what is the problem ! anyone can help ...Answered | 3 Replies | 382 Views | Created by Ahmed.Kassem - Sunday, April 16, 2017 11:38 PM | Last reply by Ahmed.Kassem - Sunday, April 23, 2017 8:25 PM -
1 Votes
Baseline Duration vs. Baseline Estimated
Baseline Duration is a copy of whatever's in the Duration field. For instance, for manually scheduled tasks, I can enter "Ask Bob" as a Duration. Baseline ...Answered | 1 Replies | 11726 Views | Created by WLID1966 - Friday, September 10, 2010 1:06 PM | Last reply by Andrew Lavinsky - Friday, September 10, 2010 1:11 PM -
0 Votes
baseline
Hi, Here you can find information about the interim plan. httpAnswered | 1 Replies | 2895 Views | Created by indiraravi - Wednesday, November 7, 2012 9:06 AM | Last reply by Robin Kruithof - Wednesday, November 7, 2012 11:53 AM -
1 Votes
Urgent-Setting time dimension on scorecard
my problem starts when i display this KPI on PPS 2007 scorecard. i cannot find a way to tell the scorecard what is the current time member (month). in other words how will ...Answered | 2 Replies | 2854 Views | Created by mhalabi - Sunday, April 26, 2009 3:05 PM | Last reply by mhalabi - Monday, April 27, 2009 6:09 AM -
1 Votes
Baseline?
/books etc... http://www.microsoft.com/project/en/us/train-learn.aspx And Baseline are not required, it all depends what isAnswered | 2 Replies | 10613 Views | Created by subnodate - Friday, June 4, 2010 5:12 AM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Friday, June 4, 2010 12:48 PM -
0 Votes
Baseline Assignment by Day Information Problem
Hi, It certainly is not a normal behavior, as Marc already confirmed. similar Project Professional 2010 Baseline values changed manually BUG i have ...Answered | 2 Replies | 8585 Views | Created by John T Purvis - Tuesday, February 22, 2011 2:10 PM | Last reply by Khurram Jamshed - Wednesday, February 23, 2011 7:35 AM -
0 Votes
Display the Baseline MS Project is using for calculation
In Project Server 2007; I would like to create a custom field that captures which Baseline the project managers are using for calculation and display it on the PWA workspace ...Answered | 2 Replies | 11243 Views | Created by rixmcx59 - Friday, June 25, 2010 7:32 PM | Last reply by rixmcx59 - Tuesday, June 29, 2010 3:35 AM -
3 Votes
Master Project doesn't display sub-projects Baseline summary
Hello Sapna, Baselining the Master project does'nt display the very Baseline of subprojects. It created a new baseline from the lastAnswered | 11 Replies | 8197 Views | Created by WLID1966 - Thursday, June 28, 2012 9:12 AM | Last reply by WLID1966 - Friday, June 29, 2012 4:24 PM -
0 Votes
Display Problem
One of my computer mother board has a display problem. When power is switched on all things goes fine but when i restart the pc or shut down and switch on within 5 ...Answered | 1 Replies | 4146 Views | Created by Binay Raj - Monday, August 2, 2010 1:35 PM | Last reply by Rick Dee - Monday, August 2, 2010 6:33 PM -
0 Votes
Update Baseline
I thought about it too but both all the tasks and selected tasks option will face the same problem if my finish plan date is different than my deadline date (that will be used as ...Answered | 5 Replies | 5662 Views | Created by Mimi Laongpanich - Wednesday, November 2, 2011 2:07 AM | Last reply by John - Project - Friday, November 4, 2011 2:16 AM -
2 Votes
Copy Existing Baseline to a different Baseline?
The naming of the feature is a bit misleading. Click Project | Set Baseline | Set Baseline Then select the 'Set interim plan' option and pick ...Answered | 5 Replies | 5044 Views | Created by Sean Pears - Thursday, August 22, 2013 4:49 AM | Last reply by Sean Pears - Thursday, August 22, 2013 8:16 PM - Items 1 to 20 of 932328 Next ›