No announcements
Found 4 threads
-
0 Votes
Can summary tasks be prevented from toggling to "Manual Scheduled" Task Mode?
Hi gang, Can summary tasks be prevented from toggling to "Manual Scheduled" Task Mode? I am using MS Project 2013 Professional, and have the Task ...Answered | 4 Replies | 1813 Views | Created by Spiro Theopoulos - Monday, April 13, 2015 6:36 PM | Last reply by Trevor Rabey - Tuesday, April 14, 2015 12:19 AM -
0 Votes
Summary tasks in Timeline in manual scheduled project template
task is manual, then it is frozen as well. I generally don't recommend manually scheduled summary tasks. Treb Gatte, ...Answered | 3 Replies | 1033 Views | Created by jjy-fin - Monday, July 6, 2015 6:28 PM | Last reply by jjy-fin - Wednesday, July 8, 2015 8:14 PM -
0 Votes
Manual Scheduled Dates Move after adding actuals
speculative drawing of timeframes. By the time your schedule is approved, all tasks should be in auto scheduled mode and manual not used. At ...Answered | 8 Replies | 1069 Views | Created by Nav Sahi - Monday, June 27, 2016 10:25 PM | Last reply by John - Project - Thursday, July 14, 2016 7:40 PM -
1 Votes
Auto vs manual scheduled - tasks must start and/or finish in specific weeks
Oh, boy, here we go again. Manual scheduled tasks is a waste of time, and you may as well use a crayon. Regardless of what you want you must first find out what you can have. Always ...Unanswered | 11 Replies | 949 Views | Created by Peperbusse - Wednesday, January 14, 2015 7:29 AM | Last reply by Dale Howard [MVP] - Thursday, January 15, 2015 4:31 PM