0 Votes
Resources not available for task assignment
SharePoint task lists see only authenticated users, not resources in the resource pool.Answered | 2 Replies | 1983 Views | Created by ScoutwestInc - Thursday, September 10, 2015 9:56 PM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Tuesday, September 22, 2015 1:37 PM -
0 Votes
Resource Assignment
You can ensure that resources are only assigned based on the RBS structure, but that will mean that you can only see the resources that belong to your RBS.Answered | 1 Replies | 9233 Views | Created by SameerwKhan - Sunday, April 10, 2011 9:09 AM | Last reply by Marc Soester [MVP] - Sunday, April 10, 2011 11:51 PM -
0 Votes
Resource Avalability - Assignment Work by Resource
As alternative, you could use reports based on cubes, there are more design options available.Answered | 2 Replies | 5793 Views | Created by Syed Yousuf Ali - Saturday, January 7, 2012 11:16 AM | Last reply by Syed Yousuf Ali - Tuesday, January 10, 2012 9:27 AM -
0 Votes
Assigning Multiple Resources to a single task
Hi Selena, Just to add to Brian's response, I strongly suggest you use a split screen.Answered | 4 Replies | 9025 Views | Created by VNEmember - Tuesday, June 5, 2012 10:45 PM | Last reply by Mike Glen - Wednesday, June 6, 2012 8:21 PM -
1 Votes
Resource Availability
There is an option of setting availability through the Resource Information dialog.Answered | 5 Replies | 8502 Views | Created by Joseph Das - Tuesday, May 1, 2012 8:12 PM | Last reply by Joseph Das - Monday, May 7, 2012 1:34 PM -
1 Votes
Assigning the Resources
Hi, Those are key concepts (task type, effort driven...) that must be understood in order to schedule correctly activities and assignments with MS Project Pro.Answered | 5 Replies | 1616 Views | Created by Experience Sharing - Monday, May 12, 2014 5:56 AM | Last reply by Guillaume Rouyre [MBA, MVP, MCC] - Monday, May 12, 2014 3:00 PM -
3 Votes
assigning overtime work to resources
Hi But one doubt My scenario is one task regular work = 8hrs/d and Actual overtime work =24 hrs/ d Performed by one resource like this i entered means Msp ...Answered | 12 Replies | 16515 Views | Created by s_samira_21 - Saturday, September 3, 2011 7:55 AM | Last reply by Shiv PMC - Sunday, November 16, 2014 11:04 AM -
0 Votes
File Server Resource Manager - File Screens
Hi Derek, On one specific folder you can set just one file screen on it.Answered | 3 Replies | 2199 Views | Created by DRUSSQAC - Saturday, October 3, 2015 1:57 PM | Last reply by Elaine Jing - Thursday, October 8, 2015 2:41 AM -
0 Votes
File Server Resource Manager File Screens
Hi, Yes, you can create a File Screen to prevent users from saving a certain file on the server and if this type of file is saved on the server, the ...Answered | 1 Replies | 642 Views | Created by Tanisend - Wednesday, March 18, 2015 5:19 PM | Last reply by Mandy Ye - Monday, March 23, 2015 7:36 AM -
0 Votes
Resource assignment based on capacity
Hi, You definitely can assign resources with 0% max unit to task.Answered | 2 Replies | 1707 Views | Created by Roshni S V - Monday, March 19, 2018 1:07 PM | Last reply by Roshni S V - Monday, March 19, 2018 1:35 PM -
1 Votes
Resource manager can not see resource assignments
You need to select View Resource Assignments in Assignment Views permission as well to enable Resource Manager to view assignment ...Answered | 3 Replies | 2104 Views | Created by Sakthi Chandrakasan - Friday, April 10, 2015 8:21 PM | Last reply by Sakthi Chandrakasan - Monday, April 13, 2015 5:14 PM -
6 Votes
Work vs Duration and Resources
I noticed in the resource assignment section it only shows a resource if they are assigned to a task within a project, but not if they are ...Answered | 8 Replies | 11522 Views | Created by Jenn Mari - Monday, June 20, 2011 9:13 PM | Last reply by Dale Howard [MVP] - Thursday, July 7, 2011 10:28 PM -
0 Votes
Resource Assignment screen vs Resource Availability Screen
Does the Publish flag control the "Resource Assignment" screen too, or does it just control the tasks that show on the "Timesheet"?Answered | 4 Replies | 1634 Views | Created by DJMadison - Thursday, August 16, 2018 1:46 PM | Last reply by DJMadison - Thursday, August 16, 2018 5:54 PM -
0 Votes
Can't assign resources to tasks
Once it is saved when opening again, the resources are now available to assign.Answered | 3 Replies | 10291 Views | Created by The Lucky PM - Wednesday, September 21, 2011 5:31 PM | Last reply by The Lucky PM - Thursday, September 22, 2011 3:26 PM -
0 Votes
Generic Resource Capacity / Avail
Hello, Define your generic resources into the resource center, either one resource with 1000% or 10 resources with 100%, then assign ...Answered | 1 Replies | 1106 Views | Created by mbarry74 - Tuesday, March 14, 2017 2:03 PM | Last reply by Jeremy Cottino - Tuesday, March 14, 2017 5:25 PM -
0 Votes
Summary Tasks on 'Resource Assignments'
Resource Center --> Select one or more resources --> Click on Resource Assignments button)?Answered | 3 Replies | 9615 Views | Created by Yoavs - Monday, May 2, 2011 6:03 AM | Last reply by Khurram Jamshed - Monday, May 2, 2011 10:38 AM -
0 Votes
How to assign a resource exclusively?
Then Resource manager would assign a named resource instead of generic.Answered | 4 Replies | 8598 Views | Created by Vygantas Raisys - Monday, April 4, 2011 7:47 PM | Last reply by Vygantas Raisys - Thursday, April 7, 2011 6:50 AM -
1 Votes
Visual Reports: Resource availability shows zero for resources
Click on Resource Work availability Report and click View.Answered | 6 Replies | 4772 Views | Created by Mekaneer - Wednesday, August 22, 2012 6:04 PM | Last reply by Roopkumar Kamat - Thursday, August 23, 2012 6:39 PM -
0 Votes
Assigning Resources to tasks
The next part depends on how the resources will be assigned.Answered | 3 Replies | 1993 Views | Created by Christine Hoaglund - Saturday, June 28, 2014 3:46 PM | Last reply by John - Project - Wednesday, July 2, 2014 6:11 PM -
0 Votes
Assigning partial resources
Hello, About the answer of Jan de Messemaeker: this will work fine, but only if no other resource is assigned to the tasks, since it creates a time constraint ...Answered | 6 Replies | 16472 Views | Created by Scott H Grosch - Wednesday, June 16, 2010 7:46 PM | Last reply by Jan De Messemaeker - Project MVP - Thursday, June 17, 2010 5:55 PM - Items 1 to 20 of 699746 Next ›