User's hours pre-popuating on timesheet - 2010 Project Server
. For 3 of these tasks hours are being pre-populated on her timesheet. The PM said he does not update the % Complete, but instead updates ...Unanswered | 2 Replies | 956 Views | Created by dennykat - Monday, June 2, 2014 3:47 PM | Last reply by dennykat - Monday, June 2, 2014 6:51 PM -
0 Votes
Timesheet - Non Project Timesheet hours
Hi, you can use the following query against the Reporting (2007/2010) or Project Service database as a starting point: USE ...Proposed | 2 Replies | 2407 Views | Created by erannaa - Friday, February 1, 2013 6:58 AM | Last reply by Renke Holert - Saturday, February 2, 2013 6:02 PM -
1 Votes
Pre-populated actual hours in PWA (project online) timesheet?
Do you care about task level hours, or just project totals? I haven't looked into what this does yet, but maybe it offers something of use? On "Timesheet ...Answered | 10 Replies | 2306 Views | Created by Kerrsol - Thursday, October 12, 2017 8:40 PM | Last reply by Alex TK - Thursday, July 18, 2019 4:34 PM -
0 Votes
project server 2010: task does not appear in user's timesheet
Hi Gaski, Thanks for the reply. The task is visible in the My Tasks section but when we try to add it manually to the timesheet as you mentioned above, the task does not ...Proposed | 3 Replies | 6680 Views | Created by geo_d - Monday, March 19, 2012 8:18 AM | Last reply by Andre Venter ZA - Monday, March 26, 2012 8:38 AM -
0 Votes
Force whole hours in timesheet Project Server 2010
Seth -- No, there is no way to prevent users from entering decimals in their Timesheets in Project Server. The best way to handle this is through a ...Proposed | 1 Replies | 1634 Views | Created by Greg Deckler (Fusion Alliance) - Thursday, August 15, 2013 3:37 AM | Last reply by Dale Howard [MVP] - Thursday, August 15, 2013 1:19 PM -
0 Votes
How to disable the synchronization of timesheet hours and project plan hours in project server 2013
hours will be sent as Status Updates to Project Manager when submitting timesheet. If that is, what you don't want any longer, disable this option. If ...Answered | 5 Replies | 687 Views | Created by Charansai.a - Tuesday, July 4, 2017 3:35 AM | Last reply by Charansai.a - Tuesday, July 4, 2017 7:47 AM -
0 Votes
Project Server 2010 Timesheet Error
reportTask updated with the some hours, report shows greater hour as per what is in project planTimesheet Cube reportUnanswered | 1 Replies | 1589 Views | Created by Dolly Pandey - Wednesday, January 29, 2014 8:49 AM | Last reply by Sachin Vashishth - Wednesday, January 29, 2014 10:59 AM -
0 Votes
MSPS- Timesheet Pre Populated Planned hours.
Hi AK, If your are talking about planned hours in a timesheet view, then you can hide planned hours in clicking on "planned" in the ...Unanswered | 3 Replies | 1554 Views | Created by Anand Kumar (AK) - Friday, November 15, 2013 9:27 AM | Last reply by Guillaume Rouyre [MBA, MVP, MCC] - Friday, November 15, 2013 1:50 PM -
0 Votes
Project Server 2010 Unapprove Timesheet
In Project server 2010 I have a user who was set as it own timesheet manager. that has since been changed to his functional manager, however has has already ...Answered | 1 Replies | 7252 Views | Created by jamesd999 - Thursday, August 11, 2011 2:37 PM | Last reply by Dale Howard [MVP] - Thursday, August 11, 2011 2:49 PM -
0 Votes
Actual Hours <> Timesheet Hours
timesheet shows only 1.5 hours - against an entirely different resource, and the 1.5 hour resource in MSPO shows 0 hours Actual! So while out timesheets are accurate, ...Unanswered | 2 Replies | 1355 Views | Created by meClark7 - Thursday, July 16, 2020 4:21 PM | Last reply by meClark7 - Saturday, July 18, 2020 12:07 AM -
1 Votes
Project Server 2010 Timesheet issue
configuring the time periods you want to use for your organisation for timesheet reporting. This hasn't changed since Project Server 2007, so ...Answered | 2 Replies | 11698 Views | Created by TheBeginner - Saturday, July 3, 2010 10:45 PM | Last reply by TheBeginner - Sunday, July 4, 2010 7:10 AM -
0 Votes
Project server timesheet Customization.
Hi , Can we get control over timesheet and do customization in Project server online. e.g If I want to add separate comments ... -
0 Votes
Project Server 2010 timesheet issue
Hi, We are timesheet in project server 2010. Once had some issue with timesheet, so he deleted the timesheet and try to create ...Answered | 3 Replies | 6841 Views | Created by arun_2014 - Thursday, September 15, 2011 2:17 AM | Last reply by arun_2014 - Tuesday, July 24, 2012 10:31 AM -
0 Votes
Timesheet hours not transferred to ms-project
Hi, we are configuring new projet on-line installation. So far, we made a project and assigned members to tasks, they can do timesheet in PWA. But the issue is : the real ...Unanswered | 5 Replies | 792 Views | Created by Vermettey - Wednesday, July 15, 2020 7:57 PM | Last reply by meClark7 - Friday, July 17, 2020 4:13 PM -
0 Votes
Project 2010 - Timesheet Actual Hours does not equal Actual Work.
Hi Lulu, Next time, try posting on the Project Server General QuestionsAnswered | 3 Replies | 11824 Views | Created by Louise Smit - Wednesday, November 10, 2010 7:45 AM | Last reply by Louise Smit - Thursday, November 11, 2010 2:59 AM -
0 Votes
Project Server 2010 - Resource Hours
still has the capability of editing the resource's hours on the Timesheet page, you you stated you are not using the Timesheet. Hope this helps. ...Answered | 3 Replies | 8121 Views | Created by A. Devita - Wednesday, June 22, 2011 5:16 PM | Last reply by Dale Howard [MVP] - Friday, June 24, 2011 2:55 PM -
0 Votes
TimeSheet in Project Server 2010
Hi Chirstophe. I have the following problem with Timesheet in Project Server 2010:Answered | 3 Replies | 9811 Views | Created by Marco Erlwein - Thursday, December 2, 2010 1:14 PM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Monday, December 20, 2010 8:38 PM -
0 Votes
Project Server 2010 Timesheet Issues
HI Mike, There are several ways you can develop a workflow in Project SErver 2010. If you go to the PRoject Server SDK you will find ...Answered | 8 Replies | 9181 Views | Created by SunnyR - Wednesday, April 27, 2011 5:25 PM | Last reply by Marc Soester [MVP] - Saturday, September 3, 2011 12:08 AM -
0 Votes
Timesheet won't display on project server 2010
Manage Timesheets). Also look at the ULS logs to get more visibility on potential issues.Answered | 3 Replies | 12286 Views | Created by ldc0618 - Friday, June 18, 2010 7:03 PM | Last reply by ldc0618 - Monday, June 21, 2010 8:53 PM -
0 Votes
project server 2010 timesheet configuration
http://www.projectserverexperts.com "We write the books on Project Server"Answered | 6 Replies | 2958 Views | Created by Debbie Clary, PMP - Tuesday, February 5, 2013 4:51 PM | Last reply by Dale Howard [MVP] - Thursday, February 7, 2013 6:36 PM - Items 1 to 20 of 2229128 Next ›