Delete assignment request - does this remove approved actual hours? RRS feed

  • Question

  • Let's say a user has been entering actual hours against a task for the past 2 months. These timesheets are all fully approved and the periods are closed.

    The user then decides they no longer want to see the task on their timesheet, so they check the task and click "Remove Task".

    If the status manager approves this delete assignment request, do the actual hours still remain?


    • Edited by project11 Thursday, December 5, 2019 5:53 AM
    Thursday, December 5, 2019 5:52 AM

All replies

  • You should test it, but since the status manager approves, it should remove the actual hours in the project plan.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Thursday, December 5, 2019 6:46 AM
    Moderator