Resource availability doesnt update RRS feed

  • Question

  • I have Project version 16 and created a file with start date the 5th of June. The Resources were entered the 5th of June. One of the resources has an availablity that was set to 100 % from the 9th of June to 30th of June. From start (5th of June) Max was 0% as expected. But today it still shows 0% and if I try to assign a task to the resource it still shows 0% for this whole week. 

    If I select Update Project the availability updates but this is not an appropriate action. Calculation is also set to On.

    If I manually change the 100% to 100% all works fine. But this should happen automatically.

    Any ideas why this doesnt work?

    Hugo


    Hugo Joergense

    Wednesday, June 10, 2020 9:58 AM