Quick link Forward and BACKWARD from a Constrained Task Date RRS feed

  • Question

  • Hi, I want to quickly link tasks Forward and Backward from a task that has a Date Constraint.
    Quick linking forward (FS) from the Date Constrained task is easy with the Link button in the Schedule field on the ribbon.
    BUT, I want to also quickly link like this Reverse/Backwards (SF) from the same Date Constrained task.

    Idea being that I change the Date Constraint date and all the tasks before and after that task move with it.

    If there was a Link Reverse button that worked like the current Link Forward button that would be awesome!

    Please help as it takes ages to re-link everything backwards (SF) when adding tasks in the middle of a group of tasks linked SF.

    I have Project Professional.


    • Edited by DS000 Friday, July 24, 2020 12:41 AM
    Friday, July 24, 2020 12:35 AM