Resource Capacity Graphs - availability incorrect RRS feed

  • Question

  • Hi all,

    I'm having some trouble with the resource utilization and resource availability graphs, as the committed hours by resource are not being considered. 

    Basically I have all three resources fully allocated to two projects, but according to the graphs all resources are available. 

    If I go to the Resource Assignments the tasks are there... 

    Maybe I'm missing some step, but all resources are committed and the projects are published...

    Any help is appreciated!


    lundi 14 octobre 2019 17:01

Toutes les réponses

  • Hi, From memory engagements are not shown in this view (use the heatmap to see the engagements).  You have to assign the resource to a task to see the impact on availability.

    Ben Howard [MVP] | web | blog | book | downloads | P2O

    lundi 14 octobre 2019 17:19
    Modérateur
  • Navigate to PWA Settings > Enterprise Data > Reporting > Choose Daily or Weekly > Save

    If this is project online it takes a while to sync the data based on the no of resource assignments !!

    Hope this helps !!

    mercredi 23 octobre 2019 05:59