PWA 2016 Adding Notes to a task in PWA RRS feed

  • Question

  • I've got administrative rights to PWA 2016 Online. I'm the owner of the project and the Project Manager with Administrative rights.

    I'm on the "Schedule" PDP within PWA (Project Web App) 2016. 

    I'm in the edit mode > View is "Project Details" the notes field is visible > notes field is greyed out.

    I can add/remove tasks, update the resource information, save, publish. The only field I can't edit is the Notes field.

    jeudi 7 novembre 2019 23:03

Toutes les réponses

  • Hi,

    Indeed you cannot edit the note field in PWA schedule PDP (since the formatting options are not supported by the schedule webpart).

    A workaround (maybe not suitable for you) is to access the note field by the team member from the "task" menu in PWA.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller


    vendredi 8 novembre 2019 08:11