    I have a problem when I declare (MS Project 2010 professional linked to MS project server 2010) an actual work in relation to an activity of my project.
    Suppose we have linked the resource R1 activity A1. The global value of work is 30 hours and the duration is 5 days. The distribution of work is 6 hours a day. The resource R1 is 100% available.

    On the Task Usage view, the work is represented as follows:
      - Day 1 >> 6h work
      - Day 2 >> 6h work
      - Day 3 >> 6h work
      - Day 4 >> 6h work
      - Day 5 >> 6h work

    When I declare the actual work for day 1, I choose its reporting 5h (I have a difference of 1 h compared with planned value). The difference of 1 hour, automatically, the project divided equally on the remaining periods:
      - Day 1 >> 6h work - 5h Actual work
      - Day 2 >> 6.25 h work
      - Day 3 >> 6.25 h work
      - Day 4 >> 6.25 h work
      - Day 5 >> 6.25 h work

    Is there a way to not split the difference between work and actual work of all periods? For example, I forrei charge the difference of 1 hour on the following period:
      - Day 1 >> 6h work - 5h Actual work
      - Day 2 >> 7h work
      - Day 3 >> 6h work
      - Day 4 >> 6h work
      - Day 5 >> 6h work


    Thank you for your help.


    • Spostato Anca Popa giovedì 20 settembre 2012 06:21 thread in inglese (Da:FAQ e articoli… nell’ambito delle tecnologie Microsoft)
    • Tipo modificato Anca Popa giovedì 20 settembre 2012 07:04 thread in inglese
    mercoledì 19 settembre 2012 17:24

Tutte le risposte

  • Ciao Francesco,

    Qui siamo in una community italiana e, come anche le linee guida del nostro forum lo dicono, scrivendo in italiano ci si capisce meglio, tanto per ora sposto il tuo thread nella sezione Off Topic.

    Grazie della comprensione,


    Anca Popa Follow ForumTechNetIt on Twitter

    Microsoft offre questo servizio gratuitamente, per aiutare gli utenti e aumentare il database dei prodotti e delle tecnologie. Il contenuto viene fornito “così come è” e non comporta alcuna responsabilità da parte dell'azienda. 

    giovedì 20 settembre 2012 07:03