  • Question

  • scenario is if user raises request approval tasks should create for Group 1 and Group 2 people. if any one approves another approval task should create for Group 3. post approval of Group 3 workflow should complete if Both the groups [1 and 2] complete approval action otherwise temporarily approved. 
    Monday, April 4, 2016 5:09 PM

Answers

  • Hi,

    If you are using SP 2010 workflow, use 2 approval workflows. One to assign parallel tasks for Group1 & groups2. Another one to assign task for Group 3.

    For the first approval workflow, click on "Approval(1)" and click on "Change the completion condition for this task process" and add below lines.

    Then add the second approval task for group3.




    Monday, April 4, 2016 6:23 PM

All replies

  • Hi,

    If you are using SP 2010 workflow, use 2 approval workflows. One to assign parallel tasks for Group1 & groups2. Another one to assign task for Group 3.

    For the first approval workflow, click on "Approval(1)" and click on "Change the completion condition for this task process" and add below lines.

    Then add the second approval task for group3.




    Monday, April 4, 2016 6:23 PM
  • Hi E,

    Is there anything update?

    Please let us know if you would like further assistance.

    Best Regards,

    Lisa Chen


    TechNet Community Support
    Please remember to mark the replies as answers if they help, and unmark the answers if they provide no help. If you have feedback for TechNet Support, contact tnmff@microsoft.com.

    Wednesday, April 6, 2016 2:57 AM
    Moderator