Task level entity data RRS feed

  • Question

  • Hi,

    I had created a Task level entity custom field "XYZ" with masters as "Yes" & "No". The PMs selected it accordingly in their projects and the actuals were entered through timesheets.

    I can see the Masters selected in the field for the tasks in the Assignment timephased cube. But the data is not getting captured in the databases. I am using PS 2010 SEM.

    Which table can i find the masters selected? Because in the reporting database it is showing NULL only.


    Cheers, Amit Wairkar

    Friday, October 18, 2019 11:10 AM