Actual Work vs. Actual Work Billable RRS feed

  • Question

  • Hi,

    What is the difference between Actual Work that we can find in Project Pro, and Actual Work Billable that we can find in an OData request?

    Thanks

    Thursday, July 25, 2019 8:23 PM

Answers

  • Hi,

    It refers to the timesheet where you can display non-billable work. Actual work = billable (default) actual work + non-billable actual work.

    Then in the report, you can segregate billable vs. non billable.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    • Marked as answer by WLID1966 Friday, July 26, 2019 5:02 PM
    Friday, July 26, 2019 6:46 AM