MS Project questions RRS feed

  • Question

  • In MS Project 2010, what does it mean/entail to have a shcedule that is:

     - Partially Baseline

     - Outdated publish dates

     - Oudated Status dates

     - Not rescheduled

     - Without deliverables

    Monday, December 3, 2012 11:46 AM

All replies

  • I'm not sure where your question is here.

    Partially baselined projects are those where all tasks are not baselined.  The additional tasks may have been added after the baseline was taken.

    Outdated published dates and outdated status dates - both fairly self explanatory. 

    Not rescheduled - incomplete work in the past

    Without deliverables - self explanatory.

    You'll need to give us more to go on here.....