MS Project resource in split shift RRS feed

  • Question

  • Hello,


    I have a project that has a day (0900-1700) and night (2300-0800) shift and where the resources can work either, but a resource may not work more than 8h per day. 


    What I'm not able to see is overallocation of a resource if I've used him on a day and night shift. In theory this would be 9h in a day (day/night) or 15 h (night/day).


    My settings are:

    • Project set at 24h calendar
    • Resources set at 24h calendar with 100% units
    • Tasks set at either day or night 


    Thanks in advance for the help,

    Dan

    Wednesday, July 17, 2019 9:38 AM