Resource Capacity Graphs - availability incorrect RRS feed

  • Question

  • Hi all,

    I'm having some trouble with the resource utilization and resource availability graphs, as the committed hours by resource are not being considered. 

    Basically I have all three resources fully allocated to two projects, but according to the graphs all resources are available. 

    If I go to the Resource Assignments the tasks are there... 

    Maybe I'm missing some step, but all resources are committed and the projects are published...

    Any help is appreciated!


    Monday, October 14, 2019 5:01 PM

All replies

  • Hi, From memory engagements are not shown in this view (use the heatmap to see the engagements).  You have to assign the resource to a task to see the impact on availability.

    Ben Howard [MVP] | web | blog | book | downloads | P2O

    Monday, October 14, 2019 5:19 PM
    Moderator
  • Navigate to PWA Settings > Enterprise Data > Reporting > Choose Daily or Weekly > Save

    If this is project online it takes a while to sync the data based on the no of resource assignments !!

    Hope this helps !!

    Wednesday, October 23, 2019 5:59 AM