  • I have question about the time sheet in EPM 2007 , Actually I want my users to report them time sheet through the epm but I want the epm to automatically calculate the task update without asking the user to import the time sheet import button in the my task page or give one of the secretary the option to just enter percentage of work completed and submitted on behalf of the user to the PM . Please advice
    Thursday, January 24, 2013 3:56 PM

All replies

  • Hi,

    would be easy to answer if you had Project Server 2010.

    For 2007, please search for "tied-mode" on http://www.codeplex.com/. There are some solutions, you may be able to use.

    Another solution to just avoid duplicate entry: Ask user to enter hours in Tasks and submit from there, e.g. on a daily basis. Let create them their timesheets AFTER entering hours for last day of timesheet period. All previously eneterd hours in Tasks will be prepopulated, so user can just send timesheet without any more update.

    Regards
    Barbara

    Thursday, January 24, 2013 7:18 PM
    Moderator
  • thanks that was helpfull