Timesheet updates when updating projects RRS feed

  • Question

  • Dear All,

    We are running EPM 2010 with timesheets in single entry mode and actuals are entered only by team members. When the PM updates his plan from MS Project Prof (Project->Update Project-> Reschedule uncompleted work to start after <today let's say>) all the undone work is moved into the future in a correct way. This can be seen in the Resource usage view and also in My Tasks in pwa. But when looking at Timesheets, the planned work in the past is not moved. It's even strange because for an unstarted task, in the Timesheet view, the starting date of a task is moved into the future but I can see planned work in the past.

    Why this view is not automatically updated and what can I do to make a sync? It is creating inconsistency between the planned work in the project plan and the planned work in timesheets.

    We have even tried to refresh the reporting DB but data is still displayed in this way.

    Thank you,

    DenisaV

    Monday, March 12, 2012 10:47 AM