Earned Value Adjustments RRS feed

  • Question

  • Earned value -I am trying to make changes to my budget.  I have added items to my fixed cost but I do not see it roll up into AC.  What am I missing? Is there another step I need to do for this to rollup?
    Thursday, April 18, 2019 1:12 AM

All replies

  • XXStudentXX99,

    Sorry but we need more information. How exactly did you "add items" to your fixed cost? What do you mean by "AC"? Did you set a baseline? Did you set a status date?

    John

    Thursday, April 18, 2019 1:39 AM
  • Have you logged any progress? There will be no actual cost on any task unless the task has an actual start date and some actual duration (except for see below). See the tracking table.

    What do you see in the cost table? Actual cost = $0 and remaining cost = $x?

    Fixed cost is usually (by default) distributed pro rata over the task duration, but can also alternatively be accrued at the start of the task, so the task can have actual cost if it has only an actual start date and no actual duration.

    Thursday, April 18, 2019 2:49 AM