TIME FORMAT IN HAMMOCK TASK RRS feed

  • Question

  • I'm creating some hammock task, and i'm having the next issue:

    Total duration of the project is 40 days and duration in hammock tasks is 39.88. 

    Somebody knows where is the problem? 

    Monday, July 8, 2019 9:51 AM

All replies

  • Blackwolf88,

    There could be many reasons why the display for days is different, you simply don't give us enough information.

    Are you using the Standard calendar or did you customize it? What is your setting for the definition of a day (File > Options> Schedule group)? Do you have any tasks with a separate Task Calendar? Do any resource have custom calendar work hours? How exactly did you set up the hammock task?

    If you could provide a screen shot or at least a detail example of the issue, then we can better assist you.

    John

    Monday, July 8, 2019 1:45 PM
  • Sorry, unfortunately i cant upload a screenshopt because the web doesnt let me. 

    Monday, July 8, 2019 2:11 PM
  • Blackwolf88,

    Okay, a screen shot can sometimes be helpful but not always. The more important information we need is a detail example and the answers to the questions I asked.

    John

    Monday, July 8, 2019 3:18 PM