Differing dates in Gantt view and the Task Usage view RRS feed

  • Question

  • Hi,

    I am facing a below issue in the MSP 2010. For certain tasks, the Start & Finish date is for the year 2014, but in the Task Usage View it is showing for the same dates but in the year 2015. Below is the screenshot for the same. How is it possible?


    Cheers, Amit Wairkar

    Friday, April 25, 2014 11:44 AM

Answers

  • Hi Amit,

    Which SP do you have? You should ensure that you're upgraded to the latest version.

    Check also for actual start and finish date.

    Then double-clicking on the grey timescale of the timephased grid, check if the "use financial period" is checked.

    Finally your file might be corrupted. In this case, use the following XML export method.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by Amit.Wairkar Saturday, April 26, 2014 3:11 AM
    Friday, April 25, 2014 12:29 PM
    Moderator
  • Hi Amit Wairkar,

    Do you have the Fiscal year set to start on something other than January?  Please check File > Options, Schedule group and check your fiscal year settings.

    • Marked as answer by Amit.Wairkar Saturday, April 26, 2014 3:11 AM
    Friday, April 25, 2014 2:45 PM
    Moderator

All replies

  • Hi Amit,

    Which SP do you have? You should ensure that you're upgraded to the latest version.

    Check also for actual start and finish date.

    Then double-clicking on the grey timescale of the timephased grid, check if the "use financial period" is checked.

    Finally your file might be corrupted. In this case, use the following XML export method.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by Amit.Wairkar Saturday, April 26, 2014 3:11 AM
    Friday, April 25, 2014 12:29 PM
    Moderator
  • Hi Amit Wairkar,

    Do you have the Fiscal year set to start on something other than January?  Please check File > Options, Schedule group and check your fiscal year settings.

    • Marked as answer by Amit.Wairkar Saturday, April 26, 2014 3:11 AM
    Friday, April 25, 2014 2:45 PM
    Moderator
  • Actually I figured out what was the problem. It was because of the Financial period. The dates are perfect now.

    Thnks Julie & Guillaume


    Cheers, Amit Wairkar

    Saturday, April 26, 2014 3:10 AM