Projects appearing incorrectly RRS feed

  • Question

  • Hi All,

    When a resource is trying to create a new task in a timesheet, he is not able to see the project, but the same project is available in the "Insert Task" and also present in task lines of the timesheet.

    Is there any limit for the projects for which tasks can be created or adding yourself to the task.

    We are using PS 2010 SEM.


    Cheers, Amit Wairkar

    Saturday, April 6, 2019 10:22 AM

Answers

  • I suppose the Project Archival group that was made was blocking those projects. Removed the name from that group and the projects are visible now.

    Cheers, Amit Wairkar

    • Marked as answer by Amit.Wairkar Monday, April 8, 2019 5:16 AM