Can project show multiple starts in the summary bar RRS feed

  • Question

  • Hello there, my question is - Can project show multiple starts in the one ID line in the summary bar rolled up?
    Wednesday, May 22, 2019 1:26 AM

All replies

  • Hi,

    yes, this is possible. To do so, add column "Rollup" to table and set to "Yes" for Project Summary task and all tasks you want to be Rolled up.

    Open Bar Styles dialog (Format - Format - Bar Styles). Set "Show For … Tasks" for "*Rolled Up Task" to "Rolled Up" only and "To" to "Task Start".

    In Bar definition at the bottom, set a shape for Start and remove shape from Middle. This should be what you are asking for:

    Regards
    Barbara


    Barbara Henhapl Blog (English/German) MVP

    Wednesday, May 22, 2019 2:31 AM