Status Manager

    Question

  •  I added a project to project server but I m not its Status manager. I open the project in project pro 2010 and I want to change the name of the status manager. But there is just my name in the list. what should I do?
    Monday, September 5, 2011 8:44 AM

Answers

  • Hi,

    Whoever you want to be the status manager, you will need to get them to open the project and insert the status manager column, their name will then appear there and they can then set the value.

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    • Marked as answer by s_samira_21 Monday, September 5, 2011 9:02 AM
    Monday, September 5, 2011 8:58 AM
    Moderator
  • For getting names listed in status manager column, who soever needs to be the status manager should open the plan atleast once from his login and save it once thats done his name would start appearing in status manager column

    let us know if this works


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com
    Monday, September 5, 2011 8:58 AM
    Moderator

All replies

  • Hi,

    Whoever you want to be the status manager, you will need to get them to open the project and insert the status manager column, their name will then appear there and they can then set the value.

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    • Marked as answer by s_samira_21 Monday, September 5, 2011 9:02 AM
    Monday, September 5, 2011 8:58 AM
    Moderator
  • For getting names listed in status manager column, who soever needs to be the status manager should open the plan atleast once from his login and save it once thats done his name would start appearing in status manager column

    let us know if this works


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com
    Monday, September 5, 2011 8:58 AM
    Moderator
  • I hoped that I had a better way!!!

    Thank you any way

    • Marked as answer by s_samira_21 Monday, September 5, 2011 9:02 AM
    • Unmarked as answer by s_samira_21 Monday, September 5, 2011 9:03 AM
    Monday, September 5, 2011 9:01 AM
  • Is there an alternate better way of changing the status manager by the PM who is the project owner as it's too cumbersome while there are too many people who need to approve initially or who keeps on changing as well during the project phase
    Thursday, May 23, 2019 3:45 PM
  • Scatterworlds --

    No, there is no easier way to change the Status Manager value.  It must be done for each task in the project by the person who will actually approve task updates from the team members assigned to the task.  This is why you should NOT have multiple people managing a project.  It makes the whole task update approval and project management process way too cumbersome.

    Also, I think it is time for you to start showing some good etiquette in the user forums.  Would you please mark a reply as the answer to your question for each of the questions you believe are answered?  Thanks!  Hope this helps.


    Dale A. Howard [MVP]

    Thursday, May 23, 2019 4:39 PM
    Moderator
  • Is it also not achievable via any any kind of customization
    Friday, May 24, 2019 9:57 AM