Timesheets getting rejected RRS feed

  • Question

  • Hi,

    We are using PS 2010 SEM. I came across a scenario where the resources who had submitted timesheets for a project got rejected mentioning the remarks as "The timesheet has been rejected because it contained at least one task that has been deleted or reassigned."

    I asked the respective Project Owner whether he had altered any lines in the MSP. He said that he just added a Resource in the Resource Sheet but never touched the task lines. The Task lines are basically created by the resources working on that project. The Project Manager has just created a Summary task for that Project.


    Cheers, Amit Wairkar

    Tuesday, June 16, 2015 10:37 AM