MSP seems to change duration and units at random RRS feed

  • Question

  • Hi,

    After altering Work of all fixed work tasks, it seems MS Project is changing or the Units or the Duration. Why is this? Is it because there was once entered a duration, so it remembers it and changes the units instead? Off course I want a task to finish as soon as possible and I want MSP to change the duration when I change Work, and not change Units.


    • Edited by Peperbusse Wednesday, January 21, 2015 10:33 AM
    Wednesday, January 21, 2015 10:32 AM

Answers

  • Hi,

    sorry, that is just how it works.

    • Change work for fixed work - behaves like fixed units
    • Change duration for fixed duration - behaves like fixed units
    • Change units for fixed units - behaves like fixed duration

    When changing the value you "fixed", system needs to use another "rule".

    Regards
    Barbara


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!