strange problem with timesheet PWA 2010 RRS feed

  • Question

  • Hi All,

     

    i have Project Server 2010 SP1 Single entry mode.

    Today i face strange problem. I have some hours reported to my Timesheet (me and my team, all hours reported to one project)

    When i modify some actuals on PWA Timesheet view - others actuals (this same task!) will change also (automaticaly after i save my timesheet).
    For example when I change value that I have for 2. January form 4h to 0h then random values in this same task will change

    I have this issue only on two projects. what should i check? 
     
     
    I don’t know what is wrong, any idea?



    Before save:

     

    after save:

    • Edited by MSPUser Monday, February 6, 2012 7:08 AM
    Tuesday, January 31, 2012 11:55 AM

All replies