  • When I update a project plan I encountered the following while I was attempting to indent & outdent a set of tasks.

    I am not able to see the circular dependency. The set of tasks I have added are independent of each other without any dependencies. 

    Thanks....

    Tuesday, May 12, 2015 9:40 PM

All replies

  • How do I resolve this issue?
    Tuesday, May 12, 2015 9:40 PM
  • Try deleting the dependencies, save the project. Then Apply the dependencies again and try to save the plan again.

    Cheers, Amit Wairkar

    Wednesday, May 13, 2015 5:22 AM
  • Hi

    Just make sure that you do not have any links with Summary Tasks. Summary tasks should not be linked to its subtasks.

    Thanks


    Manish

    Wednesday, May 13, 2015 6:59 AM