    I am working on project online 2013.I want calculate and fetch start variance ,finish variance when user set the baseline 1.

    and I want get info of baseline using client object model 2013 in project server 2013

    .


    vijay

    Friday, September 19, 2014 7:00 AM

All replies

  • Hi Vijay,

    The variance is simply the baseline n date minus the date (start, finish date...). Thus you just have to calculate this formula for n=1 (baseline 1).


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Monday, September 22, 2014 12:48 PM
    Moderator
  • Hi Vijay,

    In addition to this, I can see that you created almost 30 threads about CSOM since the beginning of september and you didn't mark any of them as an answered.

    Could you please review your threads and mark as answer the replies that actually helped you out or answer your questions so they can be closed (but still accessible) and people with a similar concern can refer to it?


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Monday, September 22, 2014 1:02 PM
    Moderator