    Is there any problems if 'Sync SharePoint Task Lists' are selected in the EPT where there are more than 2,000 projects?  I've currently got 3,000 and it is looking to expand to a lot more.

    Many thanks 

    James 




    • Edited by JamesP435 Thursday, August 3, 2017 11:05 PM
    Thursday, August 3, 2017 11:05 PM

Answers

  • Hello,

    The limit will be 2000 project sites as the project sites need to be in the PWA site collection for the task list sync process. Also, if you have more than 1000 tasks in a project it is recommended to turn the task list sync off for performance reasons.