PWA User Timesheet Error RRS feed

  • Question

  • Hello,

    I am an administrator for Project Server and had a resource submit a timesheet in error. The timesheet was approved at the time and recalled by the resource at the same time. When the resource had tried to recall, they received back an error. I delegated as the resource and tried to recall it as the user but it gets stuck with the green loading picture and never moves past that. It seems the status update was accepted when it got approved and now the timesheet is "stuck". From the user's standpoint, it shows only as "Submitted" in their Timesheet status, but somehow it does not let me delete the timesheet. The error received is saying Invalid object, timesheet failed/blocking correlation. Anyone have any idea how to resolve this? Can't seem to fix this error.

    This is the error i get in return:

    • Timesheet:
      • GeneralInvalidObject (20009). Details: id='20009' name='GeneralInvalidObject' uid='fc00fed3-1cb1-48b2-83b6-800b03b33f1d' parameter='nextApproverUID'.
    • Queue:
      • GeneralQueueJobFailed (26000) - TimesheetReview.ReviewTimesheetMessage. Details: id='26000' name='GeneralQueueJobFailed' uid='fbebdb81-29b5-416b-818d-a085a4f1d808' JobUID='e9104f34-f416-4b89-9d3e-8574a868e065' ComputerName='WEGSFES29090' GroupType='TimesheetReview' MessageType='ReviewTimesheetMessage' MessageId='1' Stage=''. For more details, check the ULS logs on machine WEGSFES29090 for entries with JobUID e9104f34-f416-4b89-9d3e-8574a868e065

    Thanks!

    Thursday, March 19, 2015 5:16 PM

All replies

  • Hi Johnny,

    Can you provide the ULS log error? Also are you with 2013/2010/2007 version?


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Friday, March 20, 2015 3:45 PM
    Moderator
  • Hi Guillaume, I cannot provide you the ULS log error since the server is hosted externally, I would have to figure a way to get that. Can you troubleshoot the issue without the ULS log? I'm running 2010 by the way.

    Monday, March 23, 2015 7:53 PM
  • Quite not easy to debug not seeing the situation, but it gets tricky if you cannot recall or delete the timesheet. Did the project manager delete update in some ways the resources' assignments in the project in the meanwhile?

    Do you have any error message stucked in the PWA queue?


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Tuesday, March 24, 2015 8:41 AM
    Moderator