    We are using Project Server 2010 SEM. Resources can create, Assign themselves to a task or insert a task for a project. 

    Our PM's are demanding that a resource should not be able to create tasks on a live project. The resource may have entered Actuals in that project.  


    Cheers, Amit Wairkar

    Saturday, April 26, 2014 7:05 AM

All replies

  • Hi Amit, 

    Try unchecking the "new task assignment" in the team member security group permissions.

    See reference below:

    http://technet.microsoft.com/en-us/library/cc197631(v=office.15).aspx

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS


    Saturday, April 26, 2014 7:17 AM
    Moderator
  • The resource is actually working on multiple projects. I want to restrict the resource from entering into a particular project

    Cheers, Amit Wairkar

    Saturday, April 26, 2014 8:57 AM
  • Hi Amit,

    You can try using the project permissions. 

    Here is an article which explains about project permissions.

    http://blogs.msdn.com/b/project/archive/2010/03/04/project-2010-project-permissions.aspx

    Cheers! Happy troubleshooting !!! Phani - MSFT Enterprise Project Management

    Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can be beneficial to other community members reading the thread.

    Saturday, April 26, 2014 11:37 AM
  • Hi Amit,

    If the resource is assigned to the project, isn't normal that it  can enter actual on it?

    In case you want to prevent the users tu use the "add rows" features in the timesheet ribbon, you can customize the ribbon to grey out the button.

    See reference below:

    http://msdn.microsoft.com/en-us/library/gg549101.aspx#pj14_ModifyPWARibbon_TimesheetRibbon

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Sunday, April 27, 2014 7:22 AM
    Moderator
  • As other have pointed out,  this may be(haven't tested) achieved thorough security permissions, by assigning specific category with specific project to users and within that category users will not have create task / relevant permissions

    But given that it is only for one project, as managing/maintaining security is quite a tedious job i would suggest it to be addressed by business process for eg. could be made a training awareness and specific resources could be trained to not add task to the project rather than trying to do a complete security thing    


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com