    I'm using Project 2010 with hosted on Project Server 2010. In my Published Project , i can see Total in Status on complete Tab is 99 %.

    but below all Tasks Completed status is 100 % . i can't find the error on this.

    Please advise on this.


    Regards, COMDINI
    Sunday, August 7, 2011 3:38 AM

Answers

  • Comdini --

    99% complete usually means that you have a Milestone task that is still not marked as 100% complete.  Try this:

    1.  Open the project and then click the View ribbon.
    2.  In the Data section of the View ribbon, click the Outline pick list button and select the All Subtasks item to completely expand the project.
    3.  Click the Filter pick list and select the "Incomplete Tasks" filter.

    Does this show a Milestone not marked as 100% complete?  If so, mark it as done.  Otherwise, let us know and we will try to help.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Sunday, August 7, 2011 2:38 PM
    Moderator