  • The ProjectData API doesn't expose the cost rate tables for a resource. Is it possible to update Cost Rate "A" and specify effective dates? I don't see this exposed in the API. Only the standard and overtime rates (of "A" which is the default) are exposed.  Anyone know if this simply isn't possible?
    středa 29. října 2014 15:53

Odpovědi

  • Hi Roland,

    As per this link and since the cost rate table is local (in the mpp), you cannot use PSI to update it. On the contrary, standard and overtime rates are enterprise data so exposed.