Managing Resource Cost Rate Tables in OData RRS feed

  • Întrebare

  • The ProjectData API doesn't expose the cost rate tables for a resource. Is it possible to update Cost Rate "A" and specify effective dates? I don't see this exposed in the API. Only the standard and overtime rates (of "A" which is the default) are exposed.  Anyone know if this simply isn't possible?
    miercuri, 29 octombrie 2014 15:53

Răspunsuri

  • Hi Roland,

    As per this link and since the cost rate table is local (in the mpp), you cannot use PSI to update it. On the contrary, standard and overtime rates are enterprise data so exposed.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marcat ca răspuns de Roland G29 miercuri, 29 octombrie 2014 16:40
    miercuri, 29 octombrie 2014 16:15
    Moderator

Toate mesajele

  • Hi Roland,

    As per this link and since the cost rate table is local (in the mpp), you cannot use PSI to update it. On the contrary, standard and overtime rates are enterprise data so exposed.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marcat ca răspuns de Roland G29 miercuri, 29 octombrie 2014 16:40
    miercuri, 29 octombrie 2014 16:15
    Moderator
  • Thanks for the info Guillaume!
    miercuri, 29 octombrie 2014 16:40