Unable to reschedule uncompleted work RRS feed

  • 问题

  • I'm a student in college and I try to use Project to conduct a simulation of a construction project. While I reschedule uncompleted work to start after a specified date, it fails. The work didn't splited as expected. However, when I try that in other project (from the examples of a tutorial book), it works. But I can't find out the reason.

    Some backgrounds: the version is Project 2010.  In my project, I only assigned materials to the tasks. and if I choose reschedule uncompleted work to stat after a specified date for entire project, that works, but which is not I need.

    Could anybody tell me why?